Construction Impacts and Key Dates

Division of College Environment

Update – September 10, 2026

Parking Lots A and B

Phase II is starting next week! This phase will bring the next significant change to the campus drives and parking areas.

Service Access Road Temporarily Closed (Buildings N102 & N105) through November 30.

  • All service and delivery traffic for N102 and N105 is redirected to the N103 parking lot, with designated delivery spaces provided
  • Traffic patterns across campus will remain directional due to active work zones
  • Vehicles cannot pass between Buildings N107 and N110 – please plan alternate routes
  • Navigation Way in front of N107 will remain closed through potentially November 30.

Starting September 17, Phase II construction will begin:

  • The new Navigation Way will be open, with traffic access to N110 and Fire Training to from Jake Alexander Blvd.
  • The service drive for N102 and N105 will be open.
  • The old Navigation Way directly in front of N101 will be permanently closed.
  • Parking Lot B will be closed.
  • Parking Lot A will be open except for the south parking lane.

All campus users are encouraged to follow posted signage, use caution when navigating construction areas, and allow additional travel time.

Campus Access and Open Areas During Closure

Access from Jake Alexander Boulevard (North Entrance):

Entering campus from Jake Alexander Boulevard, the following areas remain accessible:

  • Buildings N101, N102, N103, N105, N106 and the Amphitheatre
  • Parking Lot A
  • Parking Lot B (upper areas)
  • Service Area
  • Building N107
Access from Old Concord Road (East Side Entrance):

Entering campus from Old Concord Road, the following areas remain accessible:

  • Building N110
  • Early College
  • Fire Training Center facilities
  • Southern and eastern campus areas, including facilities near Buildings N114, N115 and N130
Delivery Access for N102 and N105 (via Rowan Tech Road):

During the service road closure, all deliveries intended for Buildings N102 and N105 must enter campus via Rowan Tech Road (North Entrance) and utilize the N103 parking lot.

Designated delivery spaces will be clearly marked within this area to accommodate service vehicles and maintain operations during construction.