North Campus
Fire Training Ground
Construction progresses at the new Fire and Emergency Services Training Facility. The block walls are starting on the upper levels of the stair tower.
As visible from above, the masonry walls are visible as well as the open shaft for the stairs. The masonry stairs are pre-fabricated off site and installed later in the project.
Outdoor Learning Center Phase II
Construction of the foundations and support walls for the amphitheater has started. Site work to align the grade with the seating and install stormwater drains has started. The brick promenade will return as construction progresses.
North Campus Solar Field
The North Campus 800Kw Solar Field is near completion with the installation of the landscaping along our Concord Road entrance.