Current Construction Projects
North Campus
Outdoor Learning Center, Phase II
Contractor: TBD
Budget: $1,700,000
Project Information
Advanced planning is currently underway for Phase II of the Outdoor Learning Center. The project will include various seating types for up to 900 people and an outdoor amphitheater.
Anticipated Completion Date: Summer 2020
Fire & Emergency Services Training Facility, Phase II
Architect: Moseley Architects
Contractor: TBD
Budget: $1,500,000
Project Information
Preconstruction contracting is currently underway for Phase II of the Fire and Emergency Services Training Facility. The Project will include a 5-story fire training tower.
Anticipated Completion Date: Summer 2020
South Campus
CBTC
College Station
Advanced Technology Center
Cabarrus Advanced Technology Center
Construction Manager At-Risk: Rodgers Builders
Budget: $17,017,979
Project Information
The Advanced Technology Center is planned to be the home to three technical programs, as well as a large and a small Industry Flex Labs which are envisioned as spaces to support innovation and training within local industry. It is envisioned that the building will house a large lecture hall, general classrooms, computer classrooms, basic and advanced labs, and associated storage and support spaces. It will have both passenger and cargo elevators to facilitate moving projects in and out of the building, as well as a loading dock and roll up doors for the Flex Labs. Students will have an information commons, large and small group study spaces, a snack bar and student lounge, and locker room with showers. Faculty and staff will be supported with a Dean/Director and Program Chair offices, cubicle areas, large and small conference rooms, work and file rooms, and a break room. The Flex Labs will be supported with dedicated office spaces, cubicles, and conference spaces.
Project Update as of February, 2018
- Educational programming underway.
- The Cabarrus Advanced Technology Center will be located at 525 John Snow Dr., Kannapolis, NC adjacent to our North Carolina Research Campus building.
- The Groundbreaking Ceremony was held January 22, 2018